Clark Building Report
Vincennes Community School Corporation

Vincennes Clark Middle School

Date: May 17, 2009
SAFETY

1. 563 Days have elapsed on this Project and there have been zero lost time
    accidents on the project.
2. ALL Contractors are reminded weekly of the importance of Safety on this Project.

QUALITY
1. Quality Control Testing Results:  
            a. Commissioning Agent inspections are ongoing by Facility Commissioning Group.  
            b. Testing & Balancing of the HVAC system is in progress by Fulton.
            c. Air Flush is set to start this week.


COST
1. Pending Change Orders

            a. COMPUTERS – Adjustment to Computers Line Item – Apple                                                   <$17,900.55>
            b. INTERACTIVITY – eBeam Edge Technology – CIM                                                                 $110,335.00
            c. Adjustment to Alternates included in Contract – Business Furniture                                              <$54,604.00>
            d. Existing Sanitary Manhole Replacement - east side of building – Wabash                                       $3,228.45
            e. Added bulkhead at Wellness Center - Hannig                                                                                $4,524.00
            f. Added bulkhead at Band Room – Hannig                                                                                      $1,515.00
            g. ADA Science Room Sink Adjustment – Heinz                                                                               $7,324.41
            h. TOTAL: 17134.54                                                                                                                       $54,422.41

2. Changes and Contingency Status:
            a. Contingency - Original:                                                                                                               $453,137.00
            b. Approved Changes:                                                                                                                  <$20,191.00>
            c. Contingency after Approved Changes:                                                                                        $432,946.00
             d. Pending Changes:                                                                                                                      $54,422.00
            e. Contingency after Pending Changes:                                                                                           $378,524.00

SCHEDULE
1. Overall Schedule:
            a. The project continues to track correctly in relation to the contracted milestone schedule.
            b. The project is on track for the scheduled Open House date of 6/24/10.

2. Activities Last 30 Days:
            a. Completed installation of gymnasium bleachers.
            b. Completed installation of casework.
            c. Completed all ceilings.
            d. Completed installation mechanical HVAC systems.
            e. Completed installation of all plumbing fixtures.
            f. Continued installation of site concrete.
            g. Started the polishing of all terrazzo.

3. Activities Next 30 Days:
            a. Complete exterior site concrete.
            b. Start asphalt paving.
            c. Complete the building air flush.
            d. Complete the installation and polish of all terrazzo.
            e. Complete all marker boards and tack boards.
            f. Start installation of LCD overhead projectors.
            g. Start installation of electronic security/surveillance system.
            h. Complete fiber optic connection between the High School and the new Middle School.
            i. Complete all interior finishes.
            j. Continue Punch List work and remediation.

COORDINATION
1. Requests for Information:
            a. 176 Requests for Information have been submitted by the Contractors.  
            b. 0 Requests for Information are pending
            c. 4.90 Days has been the average RFI response time.

2. Submittals
            a. Submittals are complete except for close-out documentation.